The headline version of the Federal Highway project is that downtown Boca Raton is losing a travel lane. That's accurate for one short segment. Between Camino Real and SE 5th Street/SE Mizner Boulevard, the outside lane is coming out. From SE 5th north to NE 8th Street/NE Mizner Boulevard, drivers keep every lane they have now, and the new bike lanes fit in by narrowing the median.

Both segments get 7-foot separated bike lanes. Drivers feel a real change on only one of them. Since August, everyone driving U.S. 1 downtown has been sitting in the same cones, so the work looks like one project. It's really two projects with different trades, and which one you use most decides how much of a difference it makes to you.

The Short Stretch That Changes the Most

The Florida Department of Transportation's project page for contract T4740 covers 1.3 miles of U.S. 1 from Camino Real to NE 8th Street/Mizner Boulevard, at an estimated construction cost of $6.3 million. General Asphalt Company won the contract with a bid of $6,362,382.40.

Most of the visible change happens at the southern end. FDOT's January 2025 design memo calls this part of the road roughly 0.3 miles that goes from six lanes to four. The section north of SE Mizner was already four lanes. On that southern stretch, the 11-foot outside lane goes away. That space, plus some taken from the median, becomes 7-foot separated bike lanes and 11-foot-wide sidewalks.

North of SE 5th Street, only the median is narrowed. The bike lanes come out of that space and the travel lanes stay. That northern segment runs past the Schmidt Boca Raton History Museum in Historic Town Hall at 71 N. Federal Highway and Sanborn Square at 72 N. Federal Highway. Drivers there gain protected bike lanes alongside them and lose no capacity.

What Drivers Get Back at Camino Real

The lane removal comes with something added. At the south end, FDOT is building a second left-turn lane for northbound drivers at Camino Real. It's also replacing the signals there with mast arms, which the agency describes as a long-term resiliency upgrade.

So the stretch losing a through lane also gains turning capacity at its busiest intersection. The 2025 public meeting also covered a speed change for that short six-lane stretch. FDOT engineers announced plans to cut it from three lanes to two northbound and lower the limit from 40 to 35 mph, according to the Boca Raton Tribune's report on the June 2025 meeting. FDOT's project page now says the speed limit within the project limits "will remain at 35 mph" during construction.

A New Way Across at Plaza Real

For people on foot, the biggest addition is a new signalized mid-block crosswalk with more lighting, just south of Plaza Real, the street that runs through Mizner Park. The project also upgrades push buttons and signal heads at every signalized intersection in the corridor, along with ADA curb ramps, pedestrian detectors, signs and pavement markings.

The crossing was the most discussed detail at FDOT's June 2025 meeting in the Downtown Library. Deputy Mayor Fran Nachlas called the bike lanes and buffers a "monumental" improvement and took questions about adding a second mid-block crossing. Frank Panellas, the engineer of record, said the city would first have to do a traffic study before FDOT could consider another one. As designed, the corridor gets one new crossing.

Trees came up at the same meeting. A longtime downtown architect and planner was among the residents who raised concerns about shade trees and preserving existing ones. Nachlas said the city was trying to coordinate and relocate some trees. FDOT project manager Vanita Saini said landscaping "would be a separate effort." The current project scope doesn't include a planting plan.

Why the City Asked for This

The project didn't start with FDOT. The agency says the lane repurposing was developed with the City of Boca Raton and at the city's request. It's listed as Palm Beach TPA Priority Project No. 17. Planners had already studied this road. The Palm Beach MPO's governing board approved a wider U.S. 1 Multimodal Corridor Study in May 2018.

The safety case is modest. FDOT reviewed crashes on the Camino Real to SE Mizner segment from January 2015 through December 2019 and counted 224, about 45 a year, including one fatality and 50 injury crashes. The same review says the corridor was not designated a high-crash corridor. FDOT's reasoning is about crossing distance: fewer lanes to cross and less time pedestrians spend in the road. The memo also admits there was no established crash-reduction factor for converting a six-lane road to four.

Where FDOT Expects the Traffic to Go

For drivers, the useful number is in FDOT's long-range traffic model. By 2040, it estimates about 4,500 daily trips, roughly 11% of projected U.S. 1 traffic through the segment, will move to other routes, mostly South Dixie Highway. The memo concluded South Dixie had enough capacity to absorb them.

That fits the two-segment design. The diversion FDOT models starts at the southern stretch, where the lane actually comes out. Public input before the design was locked was thin. The August 2020 planning workshop, held by the City and the Palm Beach TPA, got one comment in support, citing safer options for walking and biking, and one opposed, citing congestion.

Getting Around the Cones This Fall

FDOT says construction began August 20, 2026. TAPinto Boca Raton reported that the first big impact was a three-week continuous closure of the inside northbound and southbound lanes between SE 8th and SE 5th streets, starting August 24. In FDOT's October 2 to October 9 traffic report, northbound U.S. 1 between Camino Real and SE 5th Street/SE Mizner Boulevard is down to one lane through October 16 for drainage and repurposing work.

The closure rules follow the same split as the design. FDOT allows these closures:

  • Camino Real to SE 5th Street, any time: single-lane closures in either direction, with no time restrictions.
  • Camino Real to SE 5th Street, two-lane closures: northbound from 10:30 a.m. to 4:30 p.m. and from 6:30 p.m. to 7:30 a.m.; southbound from 7:30 p.m. to 12:30 p.m.
  • SE 5th Street to NE 8th Street: single-lane closures only, northbound from 7:30 p.m. to 8 a.m. and southbound from 7:30 p.m. to 11:30 a.m.

Closures are restricted to non-event days, which matters on this corridor. The city's Sanborn Square Night Market at 72 N. Federal Highway has two dates left in 2026, November 5 and a holiday-themed December 10. The free Red, White & Boca Veterans Day celebration is November 11 at Mizner Park Amphitheater, 590 Plaza Real. FDOT says access to businesses and homes stays open throughout. It posts lane closures for each upcoming week in its Palm Beach County construction reports, which are the place to check anything after October 16.

Three Finish Dates From the Same Agency

FDOT's own documents don't agree on when the work ends:

FDOT source Completion estimate
T4740 project page Summer 2027
July 2026 open-house flyer Fall 2027
October 2, 2026 traffic report Late 2027

The bid tab gives the contract 342 available days. Counted from the August 20 start, that would end in late July 2027, close to the project page's summer estimate. The newest dated document is the October traffic report, which says late 2027. If that latest estimate holds, the work will still be going more than a year from now.

The finished road will look like this. From Camino Real to SE 5th Street, there will be four travel lanes, 7-foot separated bike lanes, 11-foot sidewalks and a double left turn onto Camino Real. North of SE 5th, the same lanes as today run beside a narrower median and protected bike lanes all the way to NE 8th Street. The new lit crossing sits just south of Plaza Real.

If you're thinking about selling a home near downtown while the cones are still up, timing and presentation both matter more than usual. Karen Diaz tracks how projects like this affect showings, from which approach to suggest to buyers to how listing photos can show the street as it will look when finished. Schedule a complimentary consultation to talk through your timeline.

Karen Lee Diaz seated on a sofa in a vivid pink suit

About the Author

Karen Lee Diaz

Karen Lee Diaz is a real estate agent with Compass, serving Boca Raton and the surrounding South Florida luxury market. With a background in social work and a doctorate, Karen approaches real estate as more than transactions—she's built her career on relationships, listening closely to clients' needs and guiding them through one of life's biggest transitions, whether they're first-time homebuyers or high-net-worth investors. Bilingual in English and Spanish, she brings a rare combination of warmth, advocacy, and deep local knowledge to every deal, measuring her success not in closings but in the lasting impact she makes in her clients' lives.

Work With Karen

Get assistance in determining current property value, crafting a competitive offer, writing and negotiating a contract, and much more. Contact Karen today.